Decatur Street opens to all traffic after 14-month roadwork project
NEW ORLEANS (WVUE) - The sight of cars driving down the street is something common for most places in the world, but it’s a sight many haven’t seen down Decatur Street for more than a year.
On Monday, the Sewerage and Water Board took down the remaining fences and barriers tied to a major pipe replacement project on the street — which had prevented all vehicle traffic since September 2025.
“I might get hit by a car with all this new traffic. I’m not used to it,” Scott Barrois said.
Barrois is a server at Turkey and the Wolf, which recently opened its Decatur Street location as fencing was coming down.
He previously worked across the street at One More Pie before it had to shutter temporarily due to low sales tied to the construction woes.
Sewerage and Water Board crews dug up multiple blocks of the street to replace 100-year-old pipes and closed it off with fencing that limited how pedestrians could see and cross Decatur Street.
Barrois said the barriers made business and tips run dry.
“It was like a deserted area, a ghost town almost,” he said.
Joseph Quilio, vice president of Cajun Encounters, echoed those statements — saying foot traffic went down to a trickle for his walking tour center on Decatur Street.
However, he says he understands the need for city utilities to push forward major infrastructure projects.
“This was something that was important in terms of long term growth and sometimes you have to go through down periods to go through the highs of the highs,” Quilio said.
And so far, service workers like J.C. Brown, who works at the Market Cafe, are seeing more people out and about enjoying the improvements.
“Now that it’s open — the people are happy it’s open so they can walk freely and do as they please,” he said.
Originally, the Sewerage and Water Board said the drainage project would take less than a year to complete, but delays extended that to 14 months.
“The river was high for many months at the beginning and then they did have some archaeological finds along the way,” Public Works Director Steve Nelson said.
Nelson says that while there were construction woes, crews did what they could to finish the roadwork as quickly as possible.
And he says he wants to make changes to prevent major headaches to neighbors and businesses for the next time a street needs major drainage work.
“Doing things in bite sized pieces will certainly be the way we do things in the future,” he said.
Several Decatur Street businesses will close the road once more on Nov. 22 for a block party starting at 1 p.m.
See a spelling or grammar error in our story? Click Here to report it. Please include the headline.
Subscribe to the Fox 8 YouTube channel.
Ver nota original ↗
¿Querés un resumen rápido de esta noticia, hecho por nuestra IA?