Kirkwood withholding $1.1 million from contractor as train station stays closed
KIRKWOOD, Mo. (First Alert 4) - City records show a list of work remains on the multimillion-dollar restoration of Kirkwood’s historic train station, and passengers still cannot use the building.
Work remaining
Records from the city show a list of items marked “work required” as of Nov. 2. They include accessible routes, parking, a drinking fountain and restroom features.
Kirkwood Council Member Paul Schaefer said all of that work has to be finished, and Amtrak must complete a final inspection before the station can be used.
Kirkwood broke ground in February 2025. The city hired Raineri Construction as general contractor under a $4.7 million contract. Private donations also helped fund the project.
Schaefer said the station was originally supposed to be ready in January. The city’s project webpage says substantial work would be done by September. The city held a ribbon-cutting in September, but passengers still cannot use the station.
Temporary station
Nancy Gordon, a longtime Kirkwood resident, has volunteered at the train station for 15 years. She works the counter once a week, helping riders get ready for their trips.
“It’s enjoyable to see the people that come into the station. When people are traveling, they’re very happy. And I love Kirkwood. It’s a great place to live and the station just draws a lot of people,” Gordon said.
Gordon and other volunteers have worked out of a double-wide across the street since last spring while crews restore the station.
“They’re a little disappointed because they want to be in the station. And so would we,” Gordon said.
Council member’s concerns
Schaefer said he raised concerns about work at the site with the former city administrator.
“He could look right out his window here and see no one over here working. I can be in his office and I would tell him, hey, there’s nobody over there,” Schaefer said.
Asked by First Alert 4 Investigator David Amelotti whether Raineri is responsible for the delay, Schaefer said, “Absolutely.”
“No work was getting done. There was nobody here. Nobody was doing anything,” Schaefer said.
City withholds money
The issues came up at the Nov. 5 council meeting. City staff said key items needed for occupancy are still unresolved. Staff said the city is withholding about $1.1 million from Raineri.
David Lowell, senior project manager for Navigate Building Solutions, attended the meeting.
“We don’t know how long it’s going to take and we felt it was fair to ask for what we knew versus guessing and asking for more than we might not need,” Lowell said.
The city’s contract with Raineri calls for delay damages of $2,425 a day. The city said that if the damages are assessed through Nov. 15, they would total almost $700,000.
“We’re yanking our city staff that could be doing other things that are here chasing this. Don’t think that’s a good use of any time or any money, but we’re into it,” Schaefer said.
Contractor response
First Alert 4 Investigates asked Raineri to speak on camera about the delay and respond to the city’s concerns. The station has not received a call back.
When a First Alert 4 Investigates crew visited the station Tuesday, an employee confirmed being the new supervisor on site but declined to answer other questions.
First Alert 4 Investigates is asking whether the delay could affect the state and federal funding involved in the project.
Reopening date
The city cannot give a firm date for when the station will reopen. Schaefer said he hopes it will be by the end of the year.
Gordon said she looks forward to returning to the historic station.
“Oh, it’ll just be great. Just be able just to walk out the door and be at the tracks,” Gordon said.