Only about 100 panels left: Vantage Bridge project heads into final year

You won’t have Vantage Bridge construction to get in the way of your Thanksgiving travel plans to eastern Washington. Work has wrapped up for the year, and you only have to plan for one more year of delays.

All lanes of I-90 across the Vantage Bridge, east of Ellensburg, opened a few weeks ago, marking the end of another long construction season. The 9-foot lane restrictions were also lifted. Work to replace the bridge deck began in 2024, restricting capacity on the bridge over the Columbia River to one lane in each direction during the work, which runs from about March to November every year.

“We replaced a total of 508 of the bridge panels, and there is a total of 612, so we have just a little over 100 to do next summer when we resume work,” Washington State Department of Transportation (WSDOT) spokesperson Meagan Lott said.

Why the Vantage Bridge project is taking so long

People often ask why it’s taking so long to replace 612 bridge panels. By the time work wraps up next fall, the project will have spanned four years. You might not realize each panel is 8 feet wide and about 30 feet long. And each one is vital to the overall strength of the bridge.

To protect the 2,500-foot-long bridge and keep it from failing during this work, the contractors can only replace the panels in a very specific pattern and order. They have to maintain the appropriate load management while replacing them.

“We can’t just do all of the eastbound lanes and then all of the westbound lanes because that will cause some issues with the actual structure of the bridge,” Lott said. “We have to hopscotch around the bridge.”

And they have to keep the bridge open during the work. About 18,000 vehicles a day, many of them big rigs, use the bridge. That goes up on weekends, especially when there are concerts at the Gorge.

RELATED STORIES

Why the bridge feels bumpy, and what’s left for next year

Many drivers also ask why the bridge feels uneven when they drive it, even over the newly replaced panels.

“It’s because there’s still old panels on there and new panels that we kind of have to marry together in between winter shutdown and when we start work again,” Lott said.

Once all the panels are replaced, the contractors will go over all the lanes with a grinder and smooth everything down. That’s one of the final items on the to-do list for next year.

The plan for next year is the same as in previous years: The bridge will be reduced to one lane in each direction, with all lanes open for major holiday weekends. WSDOT thanked drivers who have made it through the delays.

“Drivers are definitely doing their due diligence by planning ahead, and we really appreciate that, but there are people that don’t travel much and get surprised,” Lott said. “People are understanding a little more than the first season.”

Only one more year to go.

The Vantage Bridge was built in 1962. The last major overhaul was in 1982. This should buy us several more decades without any major work, barring anything unexpected.

Prior to this work, which is costing about $79 million, WSDOT had to make more than a dozen emergency repairs to the bridge after finding through-deck holes.

Chris Sullivan is a traffic reporter for KIRO Newsradio. Read more of his stories here. Follow KIRO Newsradio traffic on X.

Follow @https://twitter.com/newsguysully

📄 Contenido indexado automáticamente. No es de autoría de altabusqueda.com; los derechos pertenecen a su fuente: MyNorthwest (KIRO Radio) — News.
Ver nota original ↗
🤖 Profundizá esta noticia con OIMA (IA)

¿Querés un resumen rápido de esta noticia, hecho por nuestra IA?

Respuestas de OIMA · IA, sobre esta noticia · Abrir OIMA Chat ↗
💬 0

Comentarios

También te puede interesar

Jensen Huang look-alike contest in Canada won by Seattle man
MyNorthwest (KIRO Radio) — News
A Seattle man drove three hours north and came home with a title few people can claim: Jensen Huang's top loo…
Mexico announces diplomatic protest after US denies extradition of former TV host
MyNorthwest (KIRO Radio) — News
MEXICO CITY (AP) — Mexican President Claudia Sheinbaum said Wednesday that her government would send a diplom…
Nearly 900 without power near Lake City
MyNorthwest (KIRO Radio) — News
There are nearly 900 customers without power in the Olympic Hills neighborhood, near Lake City.
A fire on a major highway surrounding Cairo kills at least 30 people, Egypt’s Health Ministry says
MyNorthwest (KIRO Radio) — News
CAIRO (AP) — A fire broke out on a major highway surrounding Cairo on Wednesday, leaving at least 30 people d…
Coastal flooding, strong winds threaten western WA over Thanksgiving
MyNorthwest (KIRO Radio) — News
Coastal flooding could pose the biggest weather threat to western Washington over Thanksgiving, with unusuall…
Former AG Rob McKenna says ICE had the authority at SEA Airport, but the approach is backfiring
MyNorthwest (KIRO Radio) — News
Rob McKenna isn't questioning whether federal immigration agents had the right to make arrests at Seattle's A…